Plans as Dependency Graphs

Intuition

"Write the report" needs "collect data" and "make charts" first; charts need data. Agents (and orchestrators, AG-17) must run sub-tasks in an order that respects dependencies — and can run independent ones in parallel.

Precise explanation

deps maps each task to the set of tasks it depends on (all tasks appear as keys). Kahn's algorithm:

  1. In-degree = number of unmet dependencies per task.
  2. Start with all tasks of in-degree 0 (sorted, for determinism — use a heap).
  3. Pop the smallest ready task, append it, decrement in-degrees of tasks that depend on it; push newly ready ones.
  4. If fewer tasks were output than exist, there is a cycle → error. Stages: repeatedly take all currently ready tasks as one stage (sorted), remove them, repeat — each stage could run in parallel.

Worked example

deps = {data: {}, outline: {}, charts: {data}, report: {data, charts, outline}} → order [data, charts, outline, report]; stages [[data, outline], [charts], [report]].

Common mistakes

  • Reversing edge direction (dependents vs dependencies).
  • Infinite loops on cycles.
  • Non-deterministic order from set iteration.

Why this matters

Build systems, data pipelines and multi-step agent plans all schedule work this way.